Hotel, North Devon

Simon WrightCase studies, News

Case Study 1: Hotel, Devon

Replacement of a failing biomass heating system with a new 330kW Hargassner wood chip boiler to provide 100% of heat and hot water load for a large hotel on North Devon Coast.

  • Turn-key installation under CDM
  • Special features: Requirement for hotel to remain fully open with no interruption in heat or hot water during the project
  • Based on the success of the project BBSM Ltd now have a long-term service contract and have been awarded an additional large piece of work to refurbish the domestic hot water to a large apartment block, fed off the biomass district heat network

Customer commented that BBSM were the best contractor they had ever worked with.